  Contract Log for ICC
Requisitioners shall be responsible for maintaining a current log of all expenditures for Institutional or Corporate Contractors (ICC) that they engage. The log shall indicate the following:
The work assignment and its purpose
The body or programme for which it is intended
The name and nationality of the individuals performing the work under the ICA
The commencement and expiration dates of the ICA
The estimated work-months required to complete the ICA
The fee or other remuneration and the basis for its calculation and payment
Any travel costs and an evaluation of the vendor's performance under the ICA